It's been a while since my last post. Here are some updates:
Poma 4 drive terminal was removed, and the hole was dug for the new, larger base terminal.
Pouring concrete, digging holes
The new Doppelmayr terminal detachable hardware. This tire bank is what allows the chairs to move slower and closer together in the terminal than when online.
Myself, posing in front of the tire bank.
Towers and sheave assemblies wait to be erected in the day lodge parking lot.
Excavating through the avalanche berm to make room for the new, larger terminal.
The view from above.
I've starting calling the new lift TedX because the resort wants to name the new lift after Ted Stevens, and it will be a proper "Express" lift since it is a high-speed detachable.